The Gravel Pit
A gravel play pit for the fenced south-west corner, drawn to scale before anything is dug.
Phase I is a footprint, an excavation and a shade plan for the fenced south-west corner. A live geometry model does the arguing: footprint shape against buildable joints, board height against gravel depth for freeboard, and a sun study that shows the fences arriving as shade at dinner rather than at noon — which makes the sail primary infrastructure, and puts its footings in the ground before a single stone.
Chapter progress
- P1The Geometry Study
- P2The Mud Kitchen
- P3Footings and the Dig
- P4Edging and Cap
- P5Stone
- P6The Sail
- Done
- 0
- In flight
- 2
- Up next
- 1
- Planned
- 3
Phases
- P1in flight
The Geometry Study
The scaled model: footprint shapes, excavation and gravel volumes, edge detail, and a sun/shade study.
- P2in flight
The Mud Kitchen
A mud kitchen counter and a low sensory table for five drop-in stainless steam-table pans, both plain dimensional-lumber butt-joint construction — drawn as plans with a full cut list and bill of materials.
- P3next
Footings and the Dig
The sail posts need 12″Ø footings below the Michigan frost line (~42″), and they sit inside the pit — poured before any stone goes in, same as anything the Phase II kitchen will bear on. Dig once.
- P4planned
Edging and Cap
2× timber edging sized so the gravel surface sits 2–3″ below the rim, with a wide flat cap that is both the containment lip and a bench.
- P5planned
Stone
Washed, rounded stone for the play surface, ordered by the cubic yard with margin for dig tolerance.
- P6planned
The Sail
Two freestanding posts at the outer footprint vertices plus a low corner at the fence intersection: a sloped plane that sheds water to the corner and shades north-east through the afternoon.